4D BIM · EVM REPORT
DEMO
synchroProject · Reference 2016-02-01 → 2017-04-26
PLANNER REPORT
Data Date 2017-04-25
Period: 2016-02-01 · daily
▾ Variance Tornado · Discipline SPI -5% -3% 0% 3% 5% Concrete & Slabs +0.0% SPI 1.00 Steel Frame +0.0% SPI 1.00 Finishing +0.0% SPI 1.00 MEP +0.0% SPI 1.00
▾ SPI · CPI Trend 0.70 0.85 1.00 1.15 1.30 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 SPI · schedule CPI · cost ▾ Discipline × Time Heatmap Concrete & Slabs Steel Frame Finishing MEP 02-01 03-09 04-14 05-21 06-27 08-03 09-09 10-16 11-23 12-30 02-05 03-14 04-19 04-25
▾ Banana Curve · Early/Late Envelope 0% 25% 50% 75% 100% 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 Early / Late envelope Baseline planned Actual progress ▾ Period Cash Flow · Bar 0.0M 0M 0.0M 6M 0.1M 11M 0.1M 17M 0.1M 22M 02-01 04-04 06-07 08-10 10-13 12-17 02-19 04-23 04-25 Period spend (PV diff) Cumulative PV ▾ Cost-Loaded Stacked Area · Discipline EV 0.0M 4.8M 9.7M 14.5M 19.3M 02-01 03-17 04-30 06-14 07-29 09-12 10-27 12-12 01-26 03-12 04-25 Concrete & Slabs Steel Frame Finishing MEP ▾ Manpower Histogram · Estimated Active Crew 0 18 36 54 72 02-01 04-04 06-07 08-10 10-13 12-17 02-19 04-23 04-25 crew · estimated (active trades × 8)
▾ Float / Slack Distribution 0 3 5 8 10 ≤0d ≤5d ≤10d ≤20d 1 ≤30d 7 ≤60d 10 ≤90d 3 ≤180d total float (days) — red = critical, green = comfortable
▾ 3-Week Look-Ahead · Active Trades 2016-02-01 2016-02-04 2016-02-07 2016-02-10 2016-02-13 2016-02-16 2016-02-19 2016-02-22 Material Procurement 9% Structural Piles 55% Pre Construction 83%
4D DASHBOARD · Full Report Page 1 / 18 · Generated 2017-04-25
4D BIM · EVM Report
DEMO
synchroProject
Reference range
2016-02-01 → 2017-04-26
Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · 4D View Page 2 / 18 · Generated 2017-04-25
DEMO
synchroProject · 4D View · daily · 2016-02-01
PLANNED · 2016-02-01
Install
Install Site Planting
Maintain
Neutral
R-L Growth
Remove
Temporary
Transparency Interpolation
ACTUAL · 2016-02-01
Install
Install Site Planting
Maintain
Neutral
R-L Growth
Remove
Temporary
Transparency Interpolation
Var · CPI
+0.0% · 0.98
Δ% · EV/AC
Section 1 Overall — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 6M 12M 18M 23M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 11,367 GBP Cum EV: 11,374 GBP Cum AC: 11,606 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Section 1 Overall Page 3 / 18 · Generated 2017-04-25
DEMO
synchroProject · Section 1 Overall · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance TOTAL 22,256,256 0.05% 0.05% +0.00% Section 1 Overall · Total 22,256,256 1 trades
Var · CPI
+0.0% · 0.98
Δ% · EV/AC
Section 1 Overall — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 6M 12M 18M 23M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 11,367 GBP Cum EV: 11,374 GBP Cum AC: 11,606 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Pre Construction Page 4 / 18 · Generated 2017-04-25
DEMO
synchroProject · Pre Construction · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Pre Construction 219,147 5.19% 5.19% +0.00% Pre Construction · Total 219,147 1 trades
Var · CPI
+0.0% · 0.98
Δ% · EV/AC
Pre Construction — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 0M 0M 0M 0M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 11,367 GBP Cum EV: 11,374 GBP Cum AC: 11,606 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Material Procurement Page 5 / 18 · Generated 2017-04-25
DEMO
synchroProject · Material Procurement · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Material Procurement 1,838,295 0.00% 0.00% +0.00% Material Procurement · Total 1,838,295 1 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Material Procurement — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 0M 1M 1M 2M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Site Construction Page 6 / 18 · Generated 2017-04-25
DEMO
synchroProject · Site Construction · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Site Construction 2,213,757 0.00% 0.00% +0.00% Structural Piles 598,128 0.00% 0.00% +0.00% Site Construction · Total 2,811,885 2 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Site Construction — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 1M 1M 2M 3M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Concrete Page 7 / 18 · Generated 2017-04-25
DEMO
synchroProject · Concrete · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Concrete 640,832 0.00% 0.00% +0.00% Slab on Deck, 1st Floor, Area 1 107,712 0.00% 0.00% +0.00% Slab on Deck, 1st Floor, Area 3 84,320 0.00% 0.00% +0.00% Slab on Grade 81,600 0.00% 0.00% +0.00% Slab on Deck, 1st Floor, Area 2 49,776 0.00% 0.00% +0.00% Concrete · Total 964,240 5 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Concrete — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 0M 1M 1M 1M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Metals Page 8 / 18 · Generated 2017-04-25
DEMO
synchroProject · Metals · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Metals 2,576,112 0.00% 0.00% +0.00% Corrugated Metal Siding 854,964 0.00% 0.00% +0.00% Metals · Total 3,431,076 2 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Metals — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 1M 2M 3M 4M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Masonry Page 9 / 18 · Generated 2017-04-25
DEMO
synchroProject · Masonry · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Masonry 205,020 0.00% 0.00% +0.00% Masonry · Total 205,020 1 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Masonry — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 0M 0M 0M 0M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Doors and Windows Page 10 / 18 · Generated 2017-04-25
DEMO
synchroProject · Doors and Windows · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Doors and Windows 858,789 0.00% 0.00% +0.00% Doors and Windows · Total 858,789 1 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Doors and Windows — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 0M 0M 1M 1M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Finishes Page 11 / 18 · Generated 2017-04-25
DEMO
synchroProject · Finishes · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Finishes 1,480,785 0.00% 0.00% +0.00% Finishes · Total 1,480,785 1 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Finishes — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 0M 1M 1M 2M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Thermal and Moisture Protection Page 12 / 18 · Generated 2017-04-25
DEMO
synchroProject · Thermal and Moisture Protection · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Thermal and Moisture Protection 525,402 0.00% 0.00% +0.00% Thermal and Moisture Protection · Total 525,402 1 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Thermal and Moisture Protection — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 0M 0M 0M 1M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Specialties Page 13 / 18 · Generated 2017-04-25
DEMO
synchroProject · Specialties · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Specialties 109,013 0.00% 0.00% +0.00% Specialties · Total 109,013 1 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Specialties — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 0M 0M 0M 0M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Conveying Systems Page 14 / 18 · Generated 2017-04-25
DEMO
synchroProject · Conveying Systems · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Conveying Systems 4,321,332 0.00% 0.00% +0.00% Conveying Systems · Total 4,321,332 1 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Conveying Systems — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 1M 2M 3M 5M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Mechanical Page 15 / 18 · Generated 2017-04-25
DEMO
synchroProject · Mechanical · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Electrical 2,081,208 0.00% 0.00% +0.00% HVAC 1,802,340 0.00% 0.00% +0.00% Plumbing 1,309,068 0.00% 0.00% +0.00% Mechanical · Total 5,192,616 3 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Mechanical — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 1M 3M 4M 5M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Project Completion Page 16 / 18 · Generated 2017-04-25
DEMO
synchroProject · Project Completion · daily · 2016-02-01
Trade Budget (GBP) % Planned % Actual Variance Project Completion 298,656 0.00% 0.00% +0.00% Project Completion · Total 298,656 1 trades
Var · CPI
+0.0% · 0.00
Δ% · EV/AC
Project Completion — Cumulative Cash Flow (GBP) PV 0M · EV 0M · AC 0M
0M 0M 0M 0M 0M 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 DATA DATE 2016-02-01 Cum PV: 0 GBP Cum EV: 0 GBP Cum AC: 0 GBP Source: Baseline synchroProject · Ref 2016-02-01 → 2017-04-26 4D BIM / EVM Dashboard
4D DASHBOARD · Planner Charts Page 17 / 18 · Generated 2017-04-25
Planner & EVM Analysis
Variance · S-curves · Heatmap · Banana envelope · Period spend · Cost stack · Manpower · Float distribution · 3-week look-ahead
▾ Variance Tornado · Discipline SPI -5% -3% 0% 3% 5% Concrete & Slabs +0.0% SPI 1.00 Steel Frame +0.0% SPI 1.00 Finishing +0.0% SPI 1.00 MEP +0.0% SPI 1.00
▾ SPI · CPI Trend 0.70 0.85 1.00 1.15 1.30 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 SPI · schedule CPI · cost ▾ Discipline × Time Heatmap Concrete & Slabs Steel Frame Finishing MEP 02-01 03-09 04-14 05-21 06-27 08-03 09-09 10-16 11-23 12-30 02-05 03-14 04-19 04-25
▾ Banana Curve · Early/Late Envelope 0% 25% 50% 75% 100% 02-01 03-27 05-22 07-17 09-11 11-07 01-02 02-27 04-23 04-25 Early / Late envelope Baseline planned Actual progress ▾ Period Cash Flow · Bar 0.0M 0M 0.0M 6M 0.1M 11M 0.1M 17M 0.1M 22M 02-01 04-04 06-07 08-10 10-13 12-17 02-19 04-23 04-25 Period spend (PV diff) Cumulative PV ▾ Cost-Loaded Stacked Area · Discipline EV 0.0M 4.8M 9.7M 14.5M 19.3M 02-01 03-17 04-30 06-14 07-29 09-12 10-27 12-12 01-26 03-12 04-25 Concrete & Slabs Steel Frame Finishing MEP ▾ Manpower Histogram · Estimated Active Crew 0 18 36 54 72 02-01 04-04 06-07 08-10 10-13 12-17 02-19 04-23 04-25 crew · estimated (active trades × 8)
▾ Float / Slack Distribution 0 3 5 8 10 ≤0d ≤5d ≤10d ≤20d 1 ≤30d 7 ≤60d 10 ≤90d 3 ≤180d total float (days) — red = critical, green = comfortable
▾ 3-Week Look-Ahead · Active Trades 2016-02-01 2016-02-04 2016-02-07 2016-02-10 2016-02-13 2016-02-16 2016-02-19 2016-02-22 Material Procurement 9% Structural Piles 55% Pre Construction 83%
4D DASHBOARD · Gantt + Critical Path Page 18 / 18 · Generated 2017-04-25
Schedule · CPM Critical Path
Activities ranked by Total Float (critical first). Red bar = critical path · Blue bar = non-critical · Amber tail = slack until LF · Red dashed line = data date cursor.
Feb 16 Mar 16 Apr 16 May 16 Jun 16 Jul 16 Aug 16 Sep 16 Oct 16 Nov 16 Dec 16 Jan 17 Feb 17 Mar 17 Apr 17 6 critical non-critical float Commissioning of Mechanical Systems ST00900 · Commissioning of Mechanical Systems
ES 2017-02-22 → EF 2017-03-07
LF 2017-03-12 · TF 5d · CRITICAL 5d Final Inspections ST00910 · Final Inspections
ES 2017-03-08 → EF 2017-03-21
LF 2017-03-25 · TF 4d · CRITICAL 4d Punch List ST00920 · Punch List
ES 2017-03-22 → EF 2017-04-04
LF 2017-04-07 · TF 3d · CRITICAL 3d Final Clean ST00930 · Final Clean
ES 2017-04-05 → EF 2017-04-18
LF 2017-04-20 · TF 2d · CRITICAL 2d Site De-Mobilization ST00940 · Site De-Mobilization
ES 2017-04-19 → EF 2017-04-25
LF 2017-04-26 · TF 1d · CRITICAL 1d Project Turnover ST00960 · Project Turnover
ES 2017-04-26 → EF 2017-04-26
LF 2017-04-26 · TF 0d · CRITICAL Notice to Proceed ST00020 · Notice to Proceed
ES 2016-02-01 → EF 2016-02-01
LF 2016-04-13 · TF 72d 72d Building Permit ST00030 · Building Permit
ES 2016-02-01 → EF 2016-02-26
LF 2016-11-10 · TF 258d 258d Award Subcontractors ST00040 · Award Subcontractors
ES 2016-02-01 → EF 2016-02-12
LF 2016-04-24 · TF 72d 72d Piles 1 ST00970 · Piles 1
ES 2016-02-08 → EF 2016-02-17
LF 2017-04-12 · TF 420d 420d Structural Steel ST00080 · Structural Steel
ES 2016-02-15 → EF 2016-05-13
LF 2016-07-21 · TF 69d 69d Glass Curtain Wall ST00090 · Glass Curtain Wall
ES 2016-02-15 → EF 2016-05-06
LF 2016-10-15 · TF 162d 162d Elevator ST00100 · Elevator
ES 2016-02-15 → EF 2016-05-13
LF 2016-12-20 · TF 221d 221d MEP Equipment ST00110 · MEP Equipment
ES 2016-02-15 → EF 2016-05-20
LF 2016-12-02 · TF 196d 196d Piles 2 ST00980 · Piles 2
ES 2016-02-18 → EF 2016-02-29
LF 2017-04-23 · TF 419d 419d Perimeter Fence ST00050 · Perimeter Fence
ES 2016-02-22 → EF 2016-02-24
LF 2017-04-26 · TF 427d 427d Temporary Hard Standing ST00060 · Temporary Hard Standing
ES 2016-02-24 → EF 2016-02-24
LF 2017-04-19 · TF 420d 420d Field Office ST00070 · Field Office
ES 2016-02-25 → EF 2016-02-26
LF 2017-04-20 · TF 419d 419d Foundation Excavation ST00120 · Foundation Excavation
ES 2016-02-29 → EF 2016-03-04
LF 2017-04-26 · TF 418d 418d Site Utilities ST00140 · Site Utilities
ES 2016-02-29 → EF 2016-04-22
LF 2017-01-02 · TF 255d 255d Piles 3 ST00990 · Piles 3
ES 2016-03-01 → EF 2016-03-04
LF 2017-04-26 · TF 418d 418d Pile Caps ST00210 · Pile Caps
ES 2016-04-04 → EF 2016-04-15
LF 2016-05-24 · TF 39d 39d Backfill / Compact Foundation Excavation ST00150 · Backfill / Compact Foundation Excavation
ES 2016-04-18 → EF 2016-04-22
LF 2016-08-18 · TF 118d 118d Grade Beams ST00220 · Grade Beams
ES 2016-04-25 → EF 2016-05-06
LF 2016-08-29 · TF 115d 115d Base Plates ST00350 · Base Plates
ES 2016-04-27 → EF 2016-04-29
LF 2016-07-21 · TF 83d 83d Structural Framing, Area 1 ST00360 · Structural Framing, Area 1
ES 2016-05-16 → EF 2016-05-25
LF 2016-07-30 · TF 66d 66d Structural Framing, Area 2 ST00370 · Structural Framing, Area 2
ES 2016-05-26 → EF 2016-06-06
LF 2016-08-10 · TF 65d 65d Plumb/ Bolt / Weld Area 1 ST00400 · Plumb/ Bolt / Weld Area 1
ES 2016-05-26 → EF 2016-06-01
LF 2017-04-26 · TF 329d 329d Structural Framing, Area 3 ST00380 · Structural Framing, Area 3
ES 2016-06-07 → EF 2016-06-20
LF 2016-08-23 · TF 64d 64d Plumb/ Bolt / Weld Area 2 ST00410 · Plumb/ Bolt / Weld Area 2
ES 2016-06-07 → EF 2016-06-13
LF 2017-04-26 · TF 317d 317d Slab on Grade, Area 1 ST01000 · Slab on Grade, Area 1
ES 2016-06-20 → EF 2016-06-20
LF 2017-04-26 · TF 310d 310d Slab on Grade, Area 2 ST01010 · Slab on Grade, Area 2
ES 2016-06-21 → EF 2016-06-21
LF 2017-04-26 · TF 309d 309d Structural Framing, Area 4 ST00390 · Structural Framing, Area 4
ES 2016-06-21 → EF 2016-07-01
LF 2016-12-20 · TF 172d 172d Plumb/ Bolt / Weld Area 3 ST00420 · Plumb/ Bolt / Weld Area 3
ES 2016-06-21 → EF 2016-06-27
LF 2016-08-29 · TF 63d 63d Slab on Grade, Area 3 ST01020 · Slab on Grade, Area 3
ES 2016-06-22 → EF 2016-06-22
LF 2017-04-26 · TF 308d 308d Plumb/ Bolt / Weld Area 4 ST00430 · Plumb/ Bolt / Weld Area 4
ES 2016-07-04 → EF 2016-07-08
LF 2016-12-24 · TF 169d 169d Crushed Gravel, Ground Floor ST00160 · Crushed Gravel, Ground Floor
ES 2016-07-11 → EF 2016-07-15
LF 2017-04-26 · TF 285d 285d Temporary Hoist ST00780 · Temporary Hoist
ES 2016-07-11 → EF 2016-11-11
LF 2017-04-26 · TF 166d 166d Slab on Deck, 1st Floor, Area 1A ST00240 · Slab on Deck, 1st Floor, Area 1A
ES 2016-07-21 → EF 2016-07-21
LF 2017-04-26 · TF 279d 279d Slab on Deck, 1st Floor, Area 1B ST00250 · Slab on Deck, 1st Floor, Area 1B
ES 2016-07-22 → EF 2016-07-22
LF 2017-04-26 · TF 278d 278d Slab on Deck, 1st Floor, Area 1C ST00260 · Slab on Deck, 1st Floor, Area 1C
ES 2016-07-25 → EF 2016-07-25
LF 2017-04-26 · TF 275d 275d Slab on Deck, 1st Floor, Area 1D ST00270 · Slab on Deck, 1st Floor, Area 1D
ES 2016-07-26 → EF 2016-07-26
LF 2017-04-26 · TF 274d 274d Slab on Deck, 1st Floor, Area 2A ST00280 · Slab on Deck, 1st Floor, Area 2A
ES 2016-07-27 → EF 2016-07-27
LF 2017-04-26 · TF 273d 273d Slab on Deck, 1st Floor, Area 2B ST00290 · Slab on Deck, 1st Floor, Area 2B
ES 2016-07-28 → EF 2016-07-28
LF 2017-04-26 · TF 272d 272d Slab on Deck, 1st Floor, Area 3A ST00300 · Slab on Deck, 1st Floor, Area 3A
ES 2016-07-29 → EF 2016-07-29
LF 2017-04-26 · TF 271d 271d Slab on Deck, 1st Floor, Area 3B ST00310 · Slab on Deck, 1st Floor, Area 3B
ES 2016-08-01 → EF 2016-08-01
LF 2017-04-26 · TF 268d 268d Blockwork / Elevator Shaft, Ground Floor ST00530 · Blockwork / Elevator Shaft, Ground Floor
ES 2016-08-01 → EF 2016-08-04
LF 2016-12-10 · TF 128d 128d Slab on Deck, 1st Floor, Area 3C ST00320 · Slab on Deck, 1st Floor, Area 3C
ES 2016-08-02 → EF 2016-08-02
LF 2017-04-26 · TF 267d 267d Slab on Deck, 2nd Floor / Low Roof ST00330 · Slab on Deck, 2nd Floor / Low Roof
ES 2016-08-03 → EF 2016-08-03
LF 2016-08-14 · TF 11d 11d Interior Stairs, Ground Floor ST00450 · Interior Stairs, Ground Floor
ES 2016-08-03 → EF 2016-08-09
LF 2017-03-06 · TF 209d 209d Slab on Deck, High Roof ST00340 · Slab on Deck, High Roof
ES 2016-08-04 → EF 2016-08-04
LF 2016-08-29 · TF 25d 25d Interior Stairs, First Floor ST00460 · Interior Stairs, First Floor
ES 2016-08-04 → EF 2016-08-10
LF 2017-03-06 · TF 208d 208d Exterior Metal Siding / Backup Framing (Front) ST00480 · Exterior Metal Siding / Backup Framing (Front)
ES 2016-08-05 → EF 2016-08-12
LF 2016-09-05 · TF 24d 24d Blockwork / Elevator Shaft, 1st Floor ST00540 · Blockwork / Elevator Shaft, 1st Floor
ES 2016-08-05 → EF 2016-08-10
LF 2016-12-15 · TF 127d 127d Blockwork / Elevator Shaft, 2nd Floor ST00550 · Blockwork / Elevator Shaft, 2nd Floor
ES 2016-08-11 → EF 2016-08-16
LF 2016-12-20 · TF 126d 126d Exterior Metal Siding / Backup Framing (Left) ST00490 · Exterior Metal Siding / Backup Framing (Left)
ES 2016-08-15 → EF 2016-08-26
LF 2016-09-16 · TF 21d 21d Glass Curtain Wall (Front) ST00590 · Glass Curtain Wall (Front)
ES 2016-08-15 → EF 2016-09-09
LF 2016-11-09 · TF 61d 61d Elevator ST00770 · Elevator
ES 2016-08-17 → EF 2016-10-25
LF 2017-02-27 · TF 125d 125d Domestic Water ST00790 · Domestic Water
ES 2016-08-17 → EF 2016-09-13
LF 2017-01-29 · TF 138d 138d Sanitary Sewer ST00800 · Sanitary Sewer
ES 2016-08-17 → EF 2016-09-13
LF 2017-01-29 · TF 138d 138d Exterior Metal Siding / Backup Framing (Back) ST00500 · Exterior Metal Siding / Backup Framing (Back)
ES 2016-08-29 → EF 2016-09-13
LF 2016-10-01 · TF 18d 18d Glass Entry Doors ST00580 · Glass Entry Doors
ES 2016-09-01 → EF 2016-09-09
LF 2017-03-12 · TF 184d 184d Punched Windows (Left) ST00600 · Punched Windows (Left)
ES 2016-09-12 → EF 2016-09-15
LF 2016-11-12 · TF 58d 58d Exterior Metal Siding / Backup Framing (Right) ST00510 · Exterior Metal Siding / Backup Framing (Right)
ES 2016-09-14 → EF 2016-09-22
LF 2016-10-09 · TF 17d 17d Punched Windows (Back) ST00610 · Punched Windows (Back)
ES 2016-09-16 → EF 2016-09-23
LF 2016-11-19 · TF 57d 57d Exterior Metal Siding / Backup Framing (Mechanical Room) ST00520 · Exterior Metal Siding / Backup Framing (Mechanical Room)
ES 2016-09-23 → EF 2016-10-10
LF 2016-10-26 · TF 16d 16d Punched Windows (Right) ST00620 · Punched Windows (Right)
ES 2016-09-26 → EF 2016-09-26
LF 2016-11-19 · TF 54d 54d Exterior Stairs ST00440 · Exterior Stairs
ES 2016-09-27 → EF 2016-10-06
LF 2017-03-06 · TF 151d 151d Exterior Doors, Frames, Hardware ST00560 · Exterior Doors, Frames, Hardware
ES 2016-09-27 → EF 2016-09-30
LF 2017-03-12 · TF 163d 163d Punched Windows (Mechanical Room) ST00630 · Punched Windows (Mechanical Room)
ES 2016-10-11 → EF 2016-10-11
LF 2017-04-26 · TF 197d 197d Mechanical Room Louvers ST00750 · Mechanical Room Louvers
ES 2016-10-11 → EF 2016-10-14
LF 2016-10-29 · TF 15d 15d Roofing, Low Roof ST00710 · Roofing, Low Roof
ES 2016-10-17 → EF 2016-11-01
LF 2016-11-13 · TF 12d 12d Roofing, High Roof ST00720 · Roofing, High Roof
ES 2016-11-02 → EF 2016-11-08
LF 2016-11-19 · TF 11d 11d Core Walls, Ground Floor ST00650 · Core Walls, Ground Floor
ES 2016-11-09 → EF 2016-11-22
LF 2017-01-03 · TF 42d 42d Roof Parapet Cap / Trim ST00730 · Roof Parapet Cap / Trim
ES 2016-11-09 → EF 2016-11-22
LF 2016-12-02 · TF 10d 10d Temporary Roof at Skylight ST00740 · Temporary Roof at Skylight
ES 2016-11-09 → EF 2016-11-09
LF 2017-04-20 · TF 162d 162d Electrical Distribution ST00870 · Electrical Distribution
ES 2016-11-09 → EF 2016-12-27
LF 2017-02-14 · TF 49d 49d Glass Skylight ST00760 · Glass Skylight
ES 2016-11-10 → EF 2016-11-16
LF 2017-04-26 · TF 161d 161d Core Walls, 1st Floor ST00660 · Core Walls, 1st Floor
ES 2016-11-23 → EF 2016-12-06
LF 2017-01-16 · TF 41d 41d Perimeter Drywall ST00680 · Perimeter Drywall
ES 2016-11-23 → EF 2016-12-20
LF 2017-01-24 · TF 35d 35d Air Handling Unit ST00820 · Air Handling Unit
ES 2016-11-23 → EF 2016-12-20
LF 2016-12-29 · TF 9d 9d Main Switch Gear / Panelboards ST00860 · Main Switch Gear / Panelboards
ES 2016-11-23 → EF 2016-12-27
LF 2017-04-26 · TF 120d 120d Core Walls, 2nd Floor ST00670 · Core Walls, 2nd Floor
ES 2016-12-07 → EF 2016-12-20
LF 2017-01-29 · TF 40d 40d Road / Parking Lot Preparation ST00170 · Road / Parking Lot Preparation
ES 2016-12-21 → EF 2017-01-17
LF 2017-03-05 · TF 47d 47d Site Improvements ST00190 · Site Improvements
ES 2016-12-21 → EF 2017-01-24
LF 2017-02-27 · TF 34d 34d Interior Doors, Frames, Hardware ST00570 · Interior Doors, Frames, Hardware
ES 2016-12-21 → EF 2016-12-28
LF 2017-03-12 · TF 74d 74d Glass Railings ST00640 · Glass Railings
ES 2016-12-21 → EF 2016-12-26
LF 2017-03-12 · TF 76d 76d Toilet Room Finishes ST00690 · Toilet Room Finishes
ES 2016-12-21 → EF 2017-01-10
LF 2017-02-18 · TF 39d 39d Misc. Finishes ST00700 · Misc. Finishes
ES 2016-12-21 → EF 2017-01-17
LF 2017-02-21 · TF 35d 35d Vertical Ductwork ST00830 · Vertical Ductwork
ES 2016-12-21 → EF 2017-01-03
LF 2017-01-11 · TF 8d 8d Electrical Devices ST00880 · Electrical Devices
ES 2016-12-28 → EF 2017-01-10
LF 2017-02-27 · TF 48d 48d Horizontal Ductwork ST00840 · Horizontal Ductwork
ES 2017-01-04 → EF 2017-02-07
LF 2017-02-14 · TF 7d 7d Toilet Room Fixtures / Trim ST00810 · Toilet Room Fixtures / Trim
ES 2017-01-11 → EF 2017-01-20
LF 2017-02-27 · TF 38d 38d Road / Parking Lot Pavement ST00180 · Road / Parking Lot Pavement
ES 2017-01-18 → EF 2017-01-25
LF 2017-03-12 · TF 46d 46d Handrails ST00470 · Handrails
ES 2017-01-18 → EF 2017-01-24
LF 2017-03-12 · TF 47d 47d Light Fixtures ST00890 · Light Fixtures
ES 2017-01-18 → EF 2017-01-24
LF 2017-02-27 · TF 34d 34d Site Plantings ST00200 · Site Plantings
ES 2017-01-25 → EF 2017-02-07
LF 2017-03-12 · TF 33d 33d Registers / Grilles / Diffusers ST00850 · Registers / Grilles / Diffusers
ES 2017-02-08 → EF 2017-02-21
LF 2017-02-27 · TF 6d 6d Certificate of Occupancy ST00950 · Certificate of Occupancy
ES 2017-04-04 → EF 2017-04-04
LF 2017-04-26 · TF 22d 22d Hover bars for ES / EF / LF / TF details · 99 activities · drag the timeline slider to move the data date cursor